Landing

BLOCKMASTER

is part of RENGY GROUP and has been involved in industrial production and construction projects since 1975. The Company is a turn-key EPC-contactor, specializing in design, engineering and general construction management of industrial solar power stations. It has its own engineering department, production facilities for metalware, steel mounting structures, modular buildings of various sizes,
junction boxes that is complemented with, its own construction team which has a track record of
managing multiple construction sites in parallel.

REALIZATION

Any type of solar power plant, including development and design, the complete set of procurement, logistics and installation, as well as commissioning services according to the local standards.

PRODUCTION

On-site metalware, modular buildings & junction boxes production.

IMPLEMENTATION

Turn key construction & installation of solar power plants on sites with different geological, hydrological and topographical surfaces.

EPC CONTRACTOR

BLOCKMASTER Team specializes in turn-key organization and management of the entire construction process of solar power stations, from design to commissioning.

Development of investment projects, advice and project support

Procurement and supply of core and auxiliary equipment and materials

Performance of general construction, civil and electrical works and commissioning

Design and financial modeling, technical and feasibility studies

Production of mounting structures, combiner boxes and modular buildings

Operations and maintenance

CONSTRUCTION OF SOLAR POWER STATIONS

BLOCKMASTER

has its own resources for the development, design, production, supply and installation of mounting structures, combiner/junction boxes and mobile/modular buildings.

The production processes of the Company have been certified according to international quality management standards ISO 9001:2009.

PROJECT
MANAGEMENT

DESIGN AND
ENGINEERING

PRODUCTION AND
PROCUREMENT

INSTALLATION AND
COMMISSIONING

HISTORY OF THE COMPANY

1971

Establishment of the project & design team to construct the metalware & modular buildings production plant as a part of the Ministry of Agricultural Construction of the Ukrainian SSR.

1975

Stage I – launch of the production facilities (20.000 m2) for manufacturing of reinforced concrete products with annual capacity of 8.000 tons.

1978

Stage II – commissioning of the production facility (45.600 m2) with annual capacity to produce 57.600 m2 of modular buildings and 1.200 tons of metalware structures and specialized equipment.

2004

Launch of trademark BLOCKMASTER.

2006

ISO certificates – accreditation of the in-house technical laboratory, introduction of international quality standards

2008

The annual production reaches 22.500 m2 of modular buildings and 3.000 tons of metalware.

2012

Construction and commissioning of the first industrial solar power plant in Ukraine financed by EBRD.

2017

Upgrade of solar power turn key EPC and mounting structures production capacity to 150 MW per annum.

OUR CAPABILITIES

SKILL

40 years of successful track record in different construction projects

QUALITY

ISO certified production and quality management systems

COMPLETE PACKAGE

Projects of various complexity, turnkey implementation from idea to commissioning

RELIABILITY

Working with leading manufacturers of materials and equipment

MULTINATIONAL PRESENCE

Completed projects in Ukraine, supplies to the former USSR, CIS and Africa

EXPERIENCE OF SOLAR POWER STATIONS CONSTRUCTION

PLANT NAME LOCATION PEAK POWER, MW THE NUMBER OF PV MODULES, PCS. LAND SIZE, HA YEAR OF COMMISSIONING
GLYBOCHOK I Vinnytsia region, Ukraine 1,4 5 874 2,5 2012
POROGI Vinnytsia region, Ukraine 4,5 18 348 10 2012
GLYBOCHOK II, phase I Vinnytsia region, Ukraine 2,5 10 098 5 2013
GNATKOV Vinnytsia region, Ukraine 5 20 328 11 2013
CHERNYATKA Vinnytsia region, Ukraine 7,7 31 614 15 2013
SHARGOROD Vinnytsia region, Ukraine 8 32 912 16 2014
GLYBOCHOK II, phase II Vinnytsia region, Ukraine 3,8 15 224 7 2015
SHARGOROD II Vinnytsia region, Ukraine 9,6 36 050 15 2016
SUVOROVO I Odessa region, Ukraine 3,2 9 288 5,8 2016
RUBANOVKA Kherson region, Ukraine 12,7 39 096 20,7 2018
MIROLYUBOVKA Kherson region, Ukraine 11,5 35 316 17 under construction
SUVOROVO II Odessa region, Ukraine 11,8 36 400 21 under construction